Overhaul and modernization of rolling mill in BONATRANS GROUP a.s.
Project Description:
In the first phase, the demolition work and excavation for the future foundations of the hoop line were the subject of implementation. Object dimensions 40 x 35 x 5m, 40 tons, 7500 m3. The construction work consisted of demolition of the existing foundation structures to the maximum extent necessary for the construction of the foundations of the new rolling line for the production of railway wheels and the expansion of the basement foundation. Waste: Soil and stones (170504) 3 350,60 t.
The following phase was the construction of foundations and service buildings, steel structures, electrical and sewerage for GO and rolling mill modernization.