Equipment for processing of lime for desulphuritazion of pig iron
Project Description:
The subject of the project was the construction of the hall. Implementation included:
SO 01 building-construction solution, ie making of foundations and steel structures. Implementation of reinforced concrete made of reinforced concrete 8×7,3 m. Implementation of a steel skeleton with a ground plan of 11×8 m and a height of 12,65 m. Built-up space 1 113 m3.
SO 02 object silos of finished products – demolition of existing reinforced concrete area 5,35x10x0,2 m and implementation of new paved areas 5,6×8,35 m and 5,35×10 m. Implementation of deep foundation by four piles to a depth of 7.5 m. Production of two feet 4,5×1,2 m with steel reinforcement.
SO 03 air condition; SO 04 rainwater sewer; SO 05 electro.