The subject of the project was earthworks, which consisted of excavations, embankments and subsequent modifications for the future route of the D48 motorway in the section Rybí – Příbor. The length of the excavation route was 5.5 km. In the course of implementation, 118,000 m3 of soil was excavated and relocated and 91,000 m3 of soil was used for embankments.