The subject of implementation was excavation (excavation works to a depth -11,9m) and demolition work during the reconstruction of the Blooming mill including waste disposal; stabilization of columns; wall stabilization; securing the walls of the excavation and continuous drainage of the building pit. Creating of wall of height H25m. Creating of cogging mill. Work took place in cramped space and were carried out continuously for 3 weeks.