Mrozek
  • Cz
  • En
  • Pl
  • COMPANY
    • MROZEK a.s.
      • ABOUT US
      • CONTACT INFORMATION
      • MACHINERY AND EQUIPMENT
      • Terms and Conditions
      • General Terms and Conditions
    • MROZEK Polska Sp. z o.o. Sp.k.
      • ABOUT COMPANY
      • CONTACT INFORMATION
      • Terms and Conditions
    • MROZEK SK, s.r.o
      • ABOUT COMPANY
      • CONTACT INFORMATION
      • TERMS AND CONDITIONS
  • SERVICES
    • DEMOLITION
    • WORK AT HEIGHTS
    • EARTHWORKS
    • CONSTRUCTION ACTIVITIES
    • RECYCLING
    • MOBILE CRANES
    • TRANSPORTATION
  • REFERENCES
  • NEWS
+420 606 795 506info@mrozek.cz
Stay connected
  • Cz
  • En
  • Pl
+420 606 795 506info@mrozek.cz
Stay connected
Mrozek Mrozek
  • COMPANY
    • MROZEK a.s.
      • ABOUT US
      • CONTACT INFORMATION
      • MACHINERY AND EQUIPMENT
      • Terms and Conditions
      • General Terms and Conditions
    • MROZEK Polska Sp. z o.o. Sp.k.
      • ABOUT COMPANY
      • CONTACT INFORMATION
      • Terms and Conditions
    • MROZEK SK, s.r.o
      • ABOUT COMPANY
      • CONTACT INFORMATION
      • TERMS AND CONDITIONS
  • SERVICES
    • DEMOLITION
    • WORK AT HEIGHTS
    • EARTHWORKS
    • CONSTRUCTION ACTIVITIES
    • RECYCLING
    • MOBILE CRANES
    • TRANSPORTATION
  • REFERENCES
  • NEWS

Projects

Demolition of a reinforced concrete chimney of the Monoyer type in Napajedla

Project Description:

The project entailed the demolition of a 51 m high chimney with a diameter ranging from approximately 4.5 to 5 m, and a head measuring 2 to 2.5 m.
The demolition was carried out up to a level of 5.4 m, which corresponds to the roof level of the building that previously enclosed the chimney. After reaching this level, the opening at the base of the chimney was sealed with a wall, and a concrete slab was constructed to cover the demolished chimney head.
The demolition process was conducted manually by workers descending from the installed protective gallery, gradually moving downwards towards the base of the chimney. Simultaneously, an excavator suspended from a crane was utilized for the remaining demolition work.
The debris resulting from the demolition was deposited inside the chimney and consistently gathered and transported to a designated waste dump.

  • Client Fatra, a.s.
  • Services Demolition
  • Date 2021
  • Link web
  • Share
Mrozek a.s.

Our goal is to deliver well-executed projects in accordance with agreed deadlines. We place
a strong emphasis on health and safety of our employees as well as minimum
environmental impact. We believe that “impossible is just a word”.

Recent Posts
  • Liebherr R974 demolishes gantry crane, Poland – “How it started vs how it’s going”